JectManager
Sign in

PMP Formula Reference

Every formula tested on the 2026 PMP exam.

← Study Guide

Earned Value Management (EVM)

Cost Variance (CV)
CV = EV – AC
Under budget (positive is good)·Over budget (negative is bad)
Schedule Variance (SV)
SV = EV – PV
Ahead of schedule·Behind schedule
Cost Performance Index (CPI)
CPI = EV / AC
CPI > 1: under budget·CPI < 1: over budget
Schedule Performance Index (SPI)
SPI = EV / PV
SPI > 1: ahead of schedule·SPI < 1: behind schedule
Estimate at Completion — Typical
EAC = BAC / CPI

Most common. Assumes current CPI holds for remainder.

Estimate at Completion — New Rate
EAC = AC + (BAC – EV)

Assumes remaining work done at planned rate.

Estimate at Completion — New Estimate
EAC = AC + ETC

Use when a new estimate for remaining work is available.

Estimate to Complete (ETC)
ETC = EAC – AC

How much more is needed to finish the project.

Variance at Completion (VAC)
VAC = BAC – EAC
Positive: under budget at end·Negative: over budget at end
To-Complete Performance Index (TCPI)
TCPI = (BAC – EV) / (BAC – AC)

Performance required on remaining work to meet BAC. TCPI > 1 = harder than current rate.

Schedule & Network

Communication Channels
N(N – 1) / 2

N = number of stakeholders

Total Float
Float = LS – ES = LF – EF

Zero float = critical path activity

Free Float
FF = ES(successor) – EF(activity)

Amount activity can slip without affecting successor's ES

Early Finish (EF)
EF = ES + Duration – 1

Used in network diagrams; some formulas use EF = ES + Duration

Late Start (LS)
LS = LF – Duration + 1

Backward pass calculation

Risk

Expected Monetary Value (EMV)
EMV = Probability × Impact

Used for decision trees and contingency reserve calculation

Total EMV (portfolio)
Total EMV = Σ(P × I) for all risks

Sum of all risk EMVs gives total exposure

Financial / Business Value

Return on Investment (ROI)
ROI = (Benefit – Cost) / Cost × 100%

Higher ROI = better investment

Net Present Value (NPV)
NPV = Σ [Cash Flow / (1 + r)^t]

r = discount rate, t = time period. Higher NPV = better project.

Payback Period
Payback = Investment / Annual Benefit

How long until investment is recovered. Lower = better.

Benefit-Cost Ratio (BCR)
BCR = Benefit / Cost

BCR > 1.0 = project delivers value. Higher BCR = better.

Internal Rate of Return (IRR)
NPV = 0 (solve for r)

The discount rate at which NPV = 0. Higher IRR = better project.

Quality (Statistics)

Standard Deviation (σ)
σ = (P – O) / 6

P = Pessimistic, O = Optimistic. Used in PERT.

PERT Estimate
E = (O + 4M + P) / 6

O = Optimistic, M = Most Likely, P = Pessimistic

Control Limits
UCL = μ + 3σ | LCL = μ – 3σ

±3 sigma contains 99.73% of all values in a normal distribution

Abbreviation Quick Reference

AbbrFull NameDefinition
BACBudget at CompletionTotal approved budget for the project
ACActual CostReal cost incurred for work performed
EVEarned ValueBudgeted cost of work actually completed
PVPlanned ValueBudgeted cost of work scheduled to be done by now
EACEstimate at CompletionExpected total cost of the project at completion
ETCEstimate to CompleteExpected cost to finish the remaining project work
VACVariance at CompletionExpected over/under budget at project end
TCPITo-Complete Performance IndexRequired CPI on remaining work to meet target
EMVExpected Monetary ValueProbability × Impact; used for risk quantification
NPVNet Present ValuePresent value of future cash flows minus investment
IRRInternal Rate of ReturnDiscount rate at which project NPV equals zero
PERTProgram Evaluation Review TechniqueWeighted average estimate: (O + 4M + P) / 6